Holt Construction provided CM GMP services for the interior fit of 20,000+ SF and installation of a 250 KW generator inclusive of upgrades to the lobby and corridor.
The challenging aspect of this project was the condensed 12 schedule requiring comprehensive value engineering within a one week time frame to recommend, approve and procure alternate materials and finishes not readily available. Given Holts aggressive procurement methodology and deep rooted subcontractor base Holt was able to pre-purchase materials and finishes in an expedited manner. In addition to the interior fit out and occurring simultaneously was the addition of a scope of a 250 KW generator in the 10th floor mechanical penthouse.
Completed
2015
Location
New York, NY
Project Scope
$6,000,000 | 20,000 SF
Design Team
Sigma 7
Follow Us