Pfizer Headquarters MER Installation
Pfizer Headquarters MER Installation

Pfizer engaged Holt as a General Contractor to install return air heaters and new fire dampers in the Mechanical Rooms of their corporate offices within Building 219.

Selective demolition of the space was performed and new piping, controls, circulating pumps, air separator, valves, and new heat exchanger were installed. Hydronic balancing of the system was completed after the installation.

The ceiling tile and grid were removed and replaced along with the wall framing to accept fire dampers. A new electrical service was also included in the project. A significant portion of the project was performed during the day when the space was occupied by Pfizer employees which required the establishment of a coordinated program with constant communication between Holt and the Pfizer personnel.

Specifications

Value

$1,100,000

Location

East 42nd Street, New York, NY

Size

15,000 Square Feet

Similar Projects

The highly sensitive environment in the pharmaceutical construction world is more clean and discreet than all markets combined.

Progenics Pharmaceuticals GMP Facility Expansion

Progenics Pharmaceuticals GMP Facility Expansion

Pfizer NYC Headquarters MER Installation