JPMorgan Chase Audit Relocation

Provisions for new FCU’s to 3 densely occupied consultant rooms, tie-ins to building’s CHW system, and new electrical panels.

 

Holt was tasked with suppling new electrical and AV infrastructure to approx. 32 offices for new furniture and tele-presence. Renovation of 8 bathrooms, including Sani glaze refurbishment to existing tiles. All work performed off-hours and weekends ons an accelerated procurement and installation schedule to meet owners date for relocating 500+ employees. Holt also had to adhere to building rules and methods of procedures from JPMorgan Chase.

CLIENT

JPMorgan Chase

LOCATION

New York, NY

PROJECT ROLE

GC

SF

79,000