Project consisted of three (3) separate and distinct phases.

 

Phase 1- Demolition and Renovation of approximately 4400 SF of existing Emergency Room support space to include new reception/registration area, waiting area, offices, security offices and Triage room.

 

Phase 2 – Convert approximately 1100 SF of existing Emergency Dept support space to a full MRI suite including all four (4) required zones.

 

Phase 3 – Add a second level, approximately 4600 SF onto an existing one level building and construct a Ten (10) private patient room Observation Unit.  The construction occurred above a fully operational Emergency Department.

 

Holt worked around the emergency room staff & patients while following Hospital Protocol and navigating through new COVID 19 safety regulations.

CLIENT

Montefiore Health System

LOCATION

Newburgh, NY

PROJECT ROLE

CM

SF

4,000